From February 2011 until December 2011 Elpee’s Steelwork manufactured and erected a 205 ton steel structure for Bilkwater Mills in Stoffberg. Manufacturing took place at our factory and was then transported to site, erected and closed with chromadeck sheeting on site. Elpee’s Steelworks was the main contractor for the project but used a sub contractor for the erection and sheeting of the structure. In additional to the tower structure Elpee’s also manufactured and erected a 2100 m² ware house.
Erection of the steelwork with a tower crane
Sheeting of the 28m high tower and warehouse in progress
On completion of the above structure , a cleaning tower structure of 28m high was supplied to the client (45t) at the same premises.